Because of the latest cost update, the average residential customer using 1,000 kWh per month will see their bill go up by about 43 cents per month.
Dominion Energy has stated that the 2.6GW Coastal Virginia Offshore Wind (CVOW) project is now approximately 50% complete and remains on track for on-time completion at the end of 2026.
President Donald Trump has long decried the use of wind power. But billions of dollars have and will flow through Virginia as public-private partnerships help create the nation’s largest offshore wind ...
A key legislative proposal aimed at strengthening Virginia’s offshore wind industry advanced to the Senate Finance and Appropriations Committee by an 11-4 vote on Monday amid the Trump ...
(WAVY) — Dominion Energy is still moving full speed ahead on the construction of the Coastal Virginia Offshore Wind (CVOW ... bill increase of $4.72 and a peak monthly bill increase of $14. ...
which is midway through constructing its $9.8 billion Coastal Virginia Offshore Wind farm off the coast of Virginia Beach and has purchased two other wind farm leases in the Atlantic Ocean? The ...
Port of Virginia’s Portsmouth Marine Terminal has welcomed the arrival of the first substation to be installed at the Coastal Virginia Offshore Wind (CVOW) project. The CS Wind Offshore and ...
RICHMOND, Va.--(BUSINESS WIRE)--Dominion Energy, Inc. (NYSE: D), today provided several updates for the Coastal Virginia Offshore Wind (CVOW) project. The 2.6 GW, fully permitted project is now ...
That includes the 2.6-gigawatt Coastal Virginia Offshore Wind project, which began construction off the coast of Virginia Beach last year. However, the order instructs the Secretary of the ...