The approval would allow the unit to construct three new combined cycle combustion turbine generation facilities, with two ...
The Richland Parish data center project, first announced in 2024, is one of the largest private capital investments in ...
Estimates suggest that the AI center will need roughly three times the amount of electricity that the city of New Orleans uses in a year ...
When Meta selected a site in Louisiana for its largest data center to date, it signed a deal with Entergy to power the site ...
State utility regulators approved a plan Wednesday to install three natural-gas fueled power plants for the tech company Meta, which needs the electricity for a massive data center it’s building in ...
Meta’s $10 billion Louisiana data center has received regulatory approval from the Louisiana Public Service Commission.
Louisianas Public Service Commission approved Entergys proposal to build three combined-cycle gas turbines and supporting transmission infrastructure to power Metas $10 billion AI data center in ...
This approval facilitates enhancements to the state’s electric grid, benefiting customers and preparing for future energy demands.
Regulators clear Entergy's multibillion-dollar plan to build three major power stations to serve Meta's massive proposed data center.
The facility is set to require more than double the energy needed to power the entire city of New Orleans during peak summer ...
The Louisiana Public Service Commission gave Entergy the green light to construct three power plants in preparation for the ...